ESTIMATING WITH ACCURACY
ESTIMATING
Before a job is entered into production, the
printer provides the customer with an estimate of job's cost, followed by a contractual agreement known as a QUOTE.
printer provides the customer with an estimate of job's cost, followed by a contractual agreement known as a QUOTE.
A prospective customer
will
want to know the cost of work to be produced for him. In printing industry,
goods produced are not normally of a standard nature. For most printing work,
however, a standard price list is impracticable due to the variety of work
handled. The cost of almost every printed job, therefore, has to be worked out
individually in advance, so that a certain profit percentage can be added and
the price quoted in the form of an estimate to the customer.
There can be few printers
having to quote for work in a competitive market who do not appreciate the need
for accurate estimating. To over-estimate may cause the loss of an order, where
as to under-estimate will result in financial loss.
Variations in prices quoted
by different firms for the same job are often considerable. No two printers
have identical plant and equipment or costs, and outputs for similar machines
vary from firm to firm. Nevertheless, much variation is due to Inaccurate
Estimating.
To make a good estimate,
one need not be an expert in arithmetic, but accuracy and orderliness are necessary
and speed is desirable. Estimates that take too long to prepare may lose a firm
the chance to gain an order.
Careless or indistinct writing
and unmethodical setting out of details or calculations greatly increase the
risk of error.
Estimating is basically a two step process.
1. Is to
analyze a job's specifications to determine the best way to produce the printed
piece and to determine whether the job should be undertaken.
2. The second
step is to estimate how much it will cost to produce the job. The estimator assigns cost ton each part of the project,
based on standard production times and budgeted hourly cost factors. The
estimator also assigns cost to materials and outside purchases and then adds a
profit margin to the job.
ESTIMATING SYSTEMS
Many different estimating
systems are in use in printing plants throughout the country. Systems based
upon Hourly rates, Fixed price list, Industry averages and Universal prices Catalogs
may be found.
An estimating system may
also include all production costs and must meet the needs of the particular
firm.
BUDGETED HOURLY COST METHOD
The budgeted hourly cost method is used in plants where
the cost of individual machine operations can be calculated.
A four steps procedure is used to obtain QUOTATIONS
for work.




Budgeted hourly costs
include the total operating cost for a given production operation for one hour.
Hourly costs are prepared by the estimator by totaling the annual expenses for
each operation or producing unit. The total annual costs for that unit are then
divided by the number of production hours in one year to give the average
hourly costs.
Here is a list of major
items that the estimator should consider when operating hourly costs.












Estimating Guidelines
Estimating requires a person who has knowledge about the
various production steps, capabilities of printing equipment.
SELECTING OPTIMUM JOB DESIGN
The estimator should always
ask the customer about job specification, such as whether the customer really
requires a specific size, type of stock, or production element. If
a small change in a job specification can reduce production costs, it is the estimator’s
responsibility to bring this to the estimator’s responsibility to bring this to
the customer’s attention.
When the estimator prepares
a worksheet jobs should be quoted several different ways in order to cost out
the most efficient production pattern. Advantages of this are the customers
choose a less expensive alternative.
The following are some specific job design factors that
should be examined in estimating virtually every job;

Ø Consider increasing or decreasing the required number of
copies requested by the customer if this will make a substantial decrease in
the customers per unit cost.
Ø
Factors
that affect length of Run economies are,
·
Paper
carton packing schedule,
·
Make-ready
time and
·
Spoilage
costs.

Ø Some jobs include elements that are either unnecessary,
arbitrary or prohibitively expensive.
Ø The estimator should question such items as special
wrapping, unnecessary folds, difficult die cutting, non standard ink colors,
unusual sizes and overly thin or extra heavy stock for the job. By eliminating
these frills you may be able to reduce costs significantly.

Ø On some jobs it may be possible to add extras that may
add little or no additional price cost but greatly increase the utility of the finished
product.

Ø The estimator should routinely cost out jobs two-four, or
eight- up to take advantage of press sizes.
PRODUCT INSPECTION.
Four main jobs of quality control may be;




Inspection may be split
into two;
1. =>Ensuring that the materials, Parts,
Components and sub-assemblies which are bought from outside firms and from other
divisions of the same firm, conform to the quality standards which have been
laid down in the new product specification.
2. =>Checking the quality of conformance of the product
during manufacture.
2.0 The Organization of Inspection.

2.1. Centralized Inspection.
This situation is
characterized by(characteristics of centralization)
(a) A direct
authority/responsibility relationship of inspection with quality control
(b) All parts of
the quality control system work for the same superior(the same status or quality).
(c) The consequent
ability of the quality manager to create a self-improving System with
inspection providing the greater part of the necessary information.(i.e should
have power to design a system which will give improvement to production)
(d) The tactical/skillful advantage of
withdrawing/indicate inspection Decision from the overriding (more important
than any other consideration) jurisdiction (authority to carry out justice) of
the production function.
(e) A greater reliance (confidence/trust in) on well prepared
product specifications with a tendency to operate rather strictly to those
specifications.
(f) A tendency to stand apart as a staff or advisory body
rather than to indulge (allow oneself) in a close association with production.
2.2. Decentralized Inspection.
The following
characteristics apply.
(a)
Inspection is closer in sympathy and in
speed of action to the particular production
unit or section.
(b) There is a much closer association with the
needs commitments of the UNIT.
(c) Each unit can more easily be given profit
responsibility. Inspection will form
part of the team and become more involved, rather than acting as an adviser and
looking on from the sidelines.
(d) In certain
circumstances the inspector and the operator can be given a joint authority for the control and quality of the work they
carry out.
This will entail the need for personal cooperation in
attaining both quality and quantity of a product, the ability to inspect work
constructively rather than rigidly, and the necessity to shut down a machine
when the quality of the work is unsatisfactory.
(e) There is the
danger that Inspectors will be overruled by production staff when outside
pressures become heavy. This situation will arise when product specifications
are not exact, when the product is behind schedule, and when incentive bonus
schemes have not been related to product quality.
The
choice of inspection system will be determined by business environment but the
primary objectives are to:


3.0.
Factors influencing the choice of system.
The choice of a system of inspection depends on the ORIGINAL IDEA.
Five facts are important in this situation,
a) The quality of
design originally fixed.
b) The clarity (clearness)
of the production specification.
c) The importance
of quality guarantees in devising bonus system.
d) The ability of
machinery to meet the specifications at the speeds in use.
e) The ability of
inspectors to measure accurately the quality characteristics which are
important.
If all these five requirements are satisfied then the
major problem confronting the operator and the inspector will have been solved.
The production specification will allow good work to be
carried out at speed acceptable to the machinery.
Operators will be rewarded
on good quality job otherwise no reward.
N.B: 1. It is quite in order for the operator and the
inspector to be working under the
Authority of the same Manager. And for the chief inspector to be made
responsible to a member of the production management team. Cooperation within
the production team is highly required.
2. The
responsibility of the inspector would extend only as far as the accurate
measurement of quality of conformance of the product.
3.
Product Quality and production quality control are two different aspects
quality.
4.0. Maintenance of Quality
Control/Improvement feedback.
Returning to the four main
jobs of quality control outlined at the beginning of this chapter, the
information for these jobs will be obtained in each case as follows
(a)
New-Product Specification-from designer, from the customer via marketing
and from existing inspection records.
(b)
Inspection-from existing records.
(c) Production Investigation-from existing inspection
records past figures and special tests.
(d) Process
Investigation-from existing records, past figures and special designed
experiments.
Quality Control information
must be communicated effectively and promptly for immediate action in
production Quality Control and in accordance with organization production
quality control policy.
5.0. Why Inspect:
Common types of inspection:
Ø Raw material Inspection.
Ø Bought-in parts and components inspection(vilivyonunuliwa
na kuletwa).
Ø Made-in parts and components inspection.(vilivyotengenezwa
humohumo ndani)
Ø Stage-by-stage inspection during production processes.
Ø Final inspection and testing.
Ø Commissioning(an instruction or command,action, task) and
field trials (examination of evidence in Law Court, by Judge)
Henceforth,
the aims of Inspection are as follows:
(a) To accept or reject an article or product.
(b) To control the process making the product.
(c)
To improve the general performance and
quality standard of the process.
6.0. Methodology of Inspection.(a
system of methods in inspection)
There are two methods of
This may use HUMAN INSPECTION METHUOD or AUTOMATIC
INSPECTION METHOD. Limitations on Human capabilities in terms of scope
and physical limitations give way to automatic inspection.
- Advantages of Automatic
Inspection.
(i)
More accurate when measurement is possible.
(ii)
More reliable.
(iii) More reproducible over a period of Time.
(iv) Not susceptible to fatigue.
(v)
More suitable
for continuous inspection and recording during processing.
- Advantages of Human Inspection.
(a) Assessment of
large numbers and varieties of fault.
(b)
The use of
intelligence and discretion (quality of being, good judgment) is classifying
defects.
(c)
The consequential assessment of faults in
relation to each other.
(d) Inspection where standards are subjective and difficult
to define.
In fact, while automatic inspection equipment is becoming
very popular, the human inspector tends to move away from simple repetitive
tasks, and to concentrate more and more on the highly complicated tasks,
demanding initiative and technical knowledge.
7.0. The Costs of Quality.
Quality costs can
be classified into three major classes
(1) Failure Costs: Money lost through products which for one reason or another do not meet the specification.
They are divided into internal and external failure costs – refer to waste in
printing works.
(2) Appraisal Costs: Money spent on inspecting products at all stages of
manufacture to determine whether or not they are defective.
(3) Prevention Costs: Money spent on ensuring that defects do not occur in
the first place.
In order to investigate quality costs, and find ways of
improving quality conformance it is important to list the type of cost which
fit into these headings.
E.g. Defectives in the Mill
Ø Low grade pulp
Ø Waste in preparation plant
Ø Machine efficiency losses
Defectives in the Field
Ø Paper returned by customers
Ø Sub-standard paper, allowances to customers
Ø Consequential loss claims
Inspection Costs
Ø Pulp inspection
Ø Chemicals and other supplies inspection (excluding fuel)
Ø Stock testing
Ø Paper testing at Machine
Ø Paper testing before dispatch
Ø Special inspection facilities
If we intend to reduce quality costs we have to find the
CAUSES for remedial steps.
PAPER AND BOARD
Wherever possible the details of paper should be
completed before considering other costs. Paper here refers to all varieties of
stock used for printing and processing. It includes:
Ø All boards
Ø Cut cards
Ø Envelops and
Ø Tags
Normally issued by the white paper warehouse for
production department, but does not include such materials as straw-boards and imitation
book covering used in the binding and finishing process.
Sample Books – Sets of paper suppliers
sample books should be kept for reference and comparison purposes. In order to
determine the stock sizes and weights available from mills and merchants, an
up-to-date paper directory containing names and addresses of mill agents and
stockiest lists of watermarks and trade names, will be found useful in tracing
the source of supply.
System of keeping sample – to avoid
sending frequently to the paper warehouse for samples of stock papers to
accompany quotations, the estimating equipment should be equipped with a
cabinet containing folded sheets of all stock lines from which samples can be
drawn.

Useful tools for the
Estimator
1. Micrometers – There are two models in general use:
i.
the heavy
desk model and
ii.
the pocket
variety.
They are used for determining the thickness of
a piece of paper or board in microns.
2.Paper weighing scale – there are two models of scales:
- Sheet
scale, and
- Template
scale.
For the sheet scales, a sheet is weighed in weight per ream or g/m2. For the template model, a cutting of paper the
size of the template is weighed. The weight per ream in demy is then given. Other model of template is g/m2.
3.Paper weight conversion slide rule: A slide rule is used for converting g/m2 to
kg/1000 sheets.
4.Calculator – For quick computations.
Factors affecting the choice of paper
and working size

i.
suitability of quality and substances which will be related to the printing
process to be used, and
ii.
economy of size.


·
the scheme
of Imposition
·
the method
of binding
·
the number
of forms to be printed
·
the
possibility of working the job more than one up
Classification of paper.
Paper can be classified into:
(i)
Quality – The trade names given to various papers and boards can
be very misleading, example,
·
Art paper
– used to mean a brush coated paper. Nowadays the term is used and can refer to
anything from a top quality brush coated esparto art to a wood free machine
coated printing
.
·
Cream wove
paper – Usually white not cream.
Quality of the paper should be submitted to
the customer.
(ii)
Paper size – The estimator
should be familiar with the British Standard (BS) for paper and board.
(iii)
International “A” paper size –
International paper size originally based on the DIN standard are of a definite
trimmed size, whereas, under the older British paper system, the finished sizes
vary considerably. The basis of international series of paper sizes is a
rectangle having an area of one square metre, the sides of which are the
proportion 1:√2. The effect of this arrangement is that if the shorter size is
doubled or the longer size halved, i.e. if the area of the sheet is doubled or
halved, the shorter side and the longer side of the new sheet are still in the
proportion 1:√2.
The description of
the “A” series consists of capital A followed by a figure e.g. A1. The higher the figure which follows the
letter, the greater is the number of subdivisions and the smaller the sheet. The
basic size has the description A0, half of A0 is A1, and half A1 is A2… etc.
Where larger dimensions are required the A is preceded by
a figure therefore 2A means the size of A0, and 4A means four times the
size of A0.
Standard Trimmed Sizes..
Designations Dimensions (mm)
2A 1189 X 1682
A0 841 X
1189
A1 594 X 841
A2 420 X 594
A3 297 X
420
A4 210 X 297
A5 148 X 210
A6 105 X
148
To meet the needs to produce these sizes it has been
agreed to adopt a PRIMARY RANGE of UNTRIMMED stock Sizes of paper in sheet.
Dimensions (mm)
RA0 860 x
1220
RA1 610 x
860
RA2 430 x 610
The letter R
indicates that this is the size in stock from which the relevant size A can be produced.
These sizes
are appropriate for a large amount of general work, but where bleed and extra
trims have to be catered for the ISO committee has prepared a recommendation
for a supplementary range.
Designation Dimensions
(mm)
SRA0 900 X
1280
SRA1 640 X 900
SRA2 450 X
640
The letters
SR indicates that this is the stock size in the supplementary Range.
The
recommended stock sizes for printing Boards are SRA1, SRA2
N.B; Other Local Standards do exist and are still
in use.
THE B SERIES
PAPERS.
The B – Series listed below is intended
primarily for Poster, Wall Charts and similar items
where the difference in size of the larger sheets in the A – Series represents
too large a jump.
Designation Dimensions (mm)
4B 2000 X 2828
2B 1414 X 2000
B0 1000 X 1414
B1 707 X 1000
B2 500 X 707
B3 353 X 500
B4 250 X 353
B5 176 X 250
The C –
Series is for envelopes or Folders suitable for
enclosing Stationeries in the A Size. The more generally used sizes are:-
Designations Dimensions (mm)
C4 229 X 24
C5 162 X 229
C6 114 X 162
DL
110 X 220
Substance; Substance
of papers is expressed in grams per square meter (g/m2)
The recommended substances for stock
sizes of printing and writing papers will be based on the
R20/R40 range.
This scale was developed and named
after a French Engineer Chares Renard
R20 series implies 20√10 (particular root of
10)
R40 series implies 40√10
Each step increases by approximately 12% over
the proceeding step i.e. is multiplied by 1.12 and rounded off.
For R series we have R10, R20, R30, R40 etc. From this
standard we can calculate the weight of paper in Kgm per 1000 sheets based on
substance given in 100gm/m²as follows.
Example;
Double medium (584 x 914) mm Substance 100gm/m
(584 x 914) m² x (100) gm/m² x 1000
sheets
(1000 x 1000) m² x (1000) gm/m² = 53.4 Kgm
Paper are ordered in terms of weight e.g. 1 ton of Double medium paper (584
x 914) mm
Caliper:
For the purpose of comparing patterns and samples it is sometimes necessary to
ascertain
The weight of papers and boards
The most accurate method of determining the weight of a
sample is to weigh a sample on a PAPER WEIGHING SCALE: Caliper here refers to the paper thickness, but
it Is not an indicator of paper of paper weight.
The Size of Paper Required:
Paper Size and desired quality
should be considered in Estimation. When a certain size is essential for
economical working, it is advisable to base the Estimate on the
nearest Standard Size paper which permits the most Economical Scheme to be
used.
Considerations when selecting paper
size
·
Number of printed pages in the type form.
·
Allowances for trimming, bleeds, gripper.
·
Lock – up between blocks.
Amount of gripper space will vary with different types of machines and
operations of printing. Trimming should be taken into consideration in the
whole process such as;
·
Before printing – trimming is important in some machines
with non standard sizes.
·
Lamination and Varnishing.
Allowances
(a) Trim: An
allowance for trim of 3 mm should be made on all edges for single leaf work,
and on head, for edge and tail and bound work various machines and printing
operations require various amounts of Trim
E.g. Letterpress - 6mm
Offset Lithography – 6mm
A special allowance possibly up to 12mm may
be necessary for some subsequent operation such as Graining, Varnishing,
Acetate, and Lamination and automatically fed binding machines.
(b) Bars:
Especially in letterpress. For small forms and labels special care should be
taken in making the proper allowances to
ensure the maximum number are printed in one sheet.
(c) Register and Grain
Direction: The direction of the
grain of the paper is very important in multi- colour register work. To keep
stretch to minimum it is
advisable to print with the long grain parallel to the impression cylinder.
Heavy papers and boards can be printed with the grain along the impression
cylinder so that they lend themselves to bend round the cylinder.
(d) Allowances for
spoilage and overs;
In estimation overs must be added to the
best quantity of paper needed to allow for proofs,
spoilage and the house files. Further quantity will
depend upon
Ø
The number of colours or workings.
Ø
Class of work
Ø
Closeness of Register
Ø
Kind of paper and machines
Ø
Length of run
It is important to make
additional allowances for any binding and outwork processes.
See the tables below
for the suggested paper wastage for letterpress and Web-fed offset.
SUGGESTED PERCENTAGE SCALE FOR CALCULATING PAPER WASTAGE FOR LETTERPRESS.
Common work(low quality print)
|
Medium work(to get good quality)
|
Very fine or close register work(i.e. colours)
|
||||
Number of
sheets
|
First colour
(%)
|
Each subsequent colour(%)
|
First colour
(%)
|
Each subsequent colour(%)
|
First colour
(%)
|
Each subsequence colour(%)
|
100 or less
|
12¹/2
|
5
|
15
|
7¹/2
|
20
|
10
|
250
|
6
|
3
|
7
|
5
|
8
|
6
|
500
|
4
|
2 ¹/2
|
5
|
3
|
6
|
4
|
1,000
|
3
|
2
|
4
|
2¹/2
|
5
|
3
|
5,000
|
2¹/2
|
1¹/2
|
3
|
2
|
3¹/2
|
2¹/2
|
10,000
|
2
|
1¹/2
|
2¹/2
|
2
|
3
|
2¹/2
|
25,000
|
1¹/2
|
1¹/2
|
2
|
1¹/2
|
2¹/2
|
2
|
50,000
|
1¹/2
|
1
|
2
|
1¹/2
|
2¹/2
|
2
|
100,000
|
1
|
1
|
1¹/2
|
1¹/2
|
2
|
2
|
These works can be grouped according to qulity shown above depending on how
much a printer pays attention to the job.
Notes;
Quantities less than 100 to have same number as
100
Add for offset litho, percent up to 10,000, ¹/2
percent over.
Add 1 percent extra each for perforating, numbering,
die-stamping, e.t.c
For varnishing allow an extra 1¹/4 percent and showcard work an extra 3¹/2
percent for mounting.
For cloth-bound work allow extra 1 percent overs.
SUGGESTED PERCENTAGE SCALE FOR CALCULATING
PAPER WASTAGE FOR WEB-FED
OFFSET CONSTANT WASTE
Wrapper .89
Core .61
Damage 1.47
|
Percentage of
Total stock
3
|
|
Running
|
Over 100,000 impressions
|
9
|
Waste
|
Over 50,000 impressions
|
10
|
Including
|
Over 25,000 impressions
|
12
|
Original
|
Over 10,000 impressions
|
14
|
make-ready
|
10,000 impressions or less
|
17
|
Additional
(The basic running waste
allowance for 2 webs 5
covers for average weight of for 3 or 4 colours 1
uncoated paper printing
one for 2 folders .5
web with two colors and delivering
for pasting 1
one unpasted signature in a
single for coated stock 6
folder. These additions must otherwise be made)
(e) Special making:
The purpose of special making is to obtain a
particular combination of weight, quality
and size, as well as the greatest number of copies without off cuts. Special making are generally obtainable in
the required quality, shade
and finish, size and weight. The minimum quantity for a
making is usually not less than one TONNE for ordinary papers.
(f) Materials handling Expenses:
In addition to the estimated cost of
the paper for the job, allowance must be made to recover the cost of
maintenance of:
·
paper
warehouse
·
storekeeper’s
Wages
·
packers
Wages
·
packing
materials
·
Transport
These
expenses are recovered on estimates by the application of an ascertained rate
per kg of paper involved. This addition should also be made to paper supplied
by the customer. Special packing and transport are not covered by this expense
and should be added as further cost COST to the job.
(g) Calculating
the number obtainable out of a sheet: -
This is important to consider
when working with odd sizes. The objective is to minimize wastage.
(h) Working Out paper Cost;
Paper and board prices falls into six categories
depending on weight i.e.
·
Smalls
(under 50 kgm)
·
50 –
200 kgm
·
200 –
500 kgm
·
1000
kgm(ex. Merchant)
·
1000kgm
(ex. Mill)
Boards are on the same basis
although they tend to be shown as per 100 boards.
Example of an
Estimate
Calculate the cost, stock size and quantity of paper required for 10,000 copies of an 8- page booklet,
trimmed size 228 x 177 mm, to be printed in two colours, closer register as one 8-page work and turn. The paper is
substance of 85gm/m² at 22 prices per kg.
SCHEDULING, LOADING AND PROJECT PLANNING
Within an organization, scheduling pertains to establish
the timing of the use of specific resources of that Organization. It relates to
the use of equipment, facilities and human activities. Scheduling occurs in
every organization, regardless of the nature of its activities.
In printing industries, production Managers must develop
schedules for workers, equipment, purchases and maintenance.
Generally, the objectives of scheduling achieve
trade-offs among conflicting goals, which includes efficient utilization of
staff, equipment, and facilities and minimization of Customer waiting time
inventories and process times.
Scheduling can either help or hinder operation strategy.
Management should not over look the important role that Scheduling plays in the
success of an organization.
The scheduling process aims at producing a schedule. A
schedule is a list which shows a systematic implementation of a scheme which
may be
·
production
scheme
·
Machine or
equipment utilization scheme
·
Working
shifts scheme
·
Print
production scheme.
Each
printing operation needs to be broken down into its constituent Jobs and
Operations. Then it is possible to load each job and operation, in correct
sequence, on the various machines.
Schedules
are always arranged in order of Priority, so determining when the work is to be
done.
Schedule
always originates from the sale department. Sales clerks often run a master
programme or schedule, from which they determine the forward commitment of the
factory/printing shop.
In
continuous production this is the straight-forward operation, involving:
·
A chart for each machine, usually large machines.
·
A list of output capacity for each product which can be
produced on that machine.
In batch and
jobbing work the forward commitments are more difficult to determine.
2. PRINCIPLES OF
SCHEDULING.
The aims of scheduling are simply to
arrange the work of the production unit in such a way that
(a)
All orders are delivered on time
(b)
Orders are completed at minimum total cost
Following
from this it is possible to identify principles of scheduling which apply to
all cases.
·
Operations should be of short duration
·
Different operations should have approximately the same
duration
·
All machine groups, or departments, should have an even
load
·
As far as possible, work-centre should be employed in the
same sequence.
These
principles describe accurately many forms of continuous production. The
continuous or flow production unit gives higher utilization of assets.
3. AIMS OF
LOADING.
There a number of aims of loading,
which may be identified, are the following.
·
To reduce material waiting Time
·
To reduce set-up time
·
To reduce operator and machine idle time
·
To give information for delivery estimates
·
To produce an even plant load from new schedule
·
To balance labour, plant capacity and work load
·
To spotlight over and under-utilized plant and machinery.
These aims are often complementary.
4. SCHEDULING
PROBLEM.
The problem of scheduling can often be
quite intractable, particularly in the jobbing shop, where it may be extremely
difficult to achieve many of the aims of loading given above.
The problem is made up of:
(a)
A number of machines
(b)
A number of jobs
(c)
Each job has a sequence of operations.
(d)
Each operation has a given time.
With a number of machines
scheduling problem becomes more complex.
4.1 SCHEDULING RULES.
Scheduling is a queuing problem which
involves describing the position of each job in the queue and the priority given to each job. Some of the
rules include the following;
(a)
Each job joins the end of the queue
(b)
The job with the longest operation time always goes first
(c)
The job with the shortest operation time always goes
first
(d)
The job with the highest value goes first
(e)
Last in, first out (LIFO)
(f)
Rank according to earliest delivery date
(g)
Rank according to shortest total job time i.e. the sum of
the individual operation times.
The usefulness of scheduling rules lies in the discipline they force on the
planning staff, rather than on their ability to provide Optimality.
The
scheduling situation is dynamic, and hence one rarely suffices for all
situations.
N.B: Scheduling and loading deal with the sequence
of performing jobs. This must be carried out in relation to the capacity of the plant one of
the aims of loading is to balance loads against the available capacity of the
machines in order to bring to light any badly overloaded or under loaded machinery.
Every job is loaded and off-loaded in the same units, with the date of loading
and unloading. Each job has its standard time written besides it, and the total
of these standard times may then be compared with actual running times.
TYPES OF
PRODUCTION PLANNING
1. Batch Working. This type of manufacture is generally
considered to be among the most difficult for good Production Planning and control.
The problems are brought about by the
complicated route ring which can take place within the factory as batches of work
move around from shop to shop.








2. Continuous Production. This is typified by the continuous production of solids or liquids on a
large scale, by the line production of components and by the assembly line.
The important Planning factors are as follows;







3. Project Planning.
When a single, large project is
being planned the product-planning activity is concerned with a complicated series of OPERATIONS, which
are to be carried only once. Usually there are no pre-arranged Layouts, methods
or times and often the product has still to be designed. The problem here is
–fold;
a) Working out the relationships between all the
different operations and activities.
b)
Estimating
the durations of activities.
c)
Channeling
all materials and other resources to the correct place at the moment of need.
The complexity involved in Project
Planning is usually tackled by various efficient planning techniques notably


These Project planning techniques
have the following features;







Project Planning will



PERT and CPM facilitates planning and
Coordination of large projects. Gantt chart may also be used.
4. Use of Computers in Production planning.
Computers are very useful in
Production planning through the use of appropriate soft wares for planning e.g.
MS-Project and for estimating costs. In big
project computers can be used in various aspects of production planning such as
in;





ESTIMATING
COMPOSITION
COMPOSITION.
A clear conception of the proposed job should be made including all the
copy to be set. Make sure to avoid the pitfalls, which arise when work has to
be quoted for without seeing any copy;
Ø Decide broadly the method of working.
Ø Determine the number of pages the copy will make
(casting off).
Ø Break the job down into the sequence of
direct operation.
Ø Calculate times for each operation and extend at the
relation hourly rate.
A bad manuscript may add very considerably to the compositors or lay
board operator’s times. Foreign language setting will not take longer to set,
but may involve the employment of an outside translator to prepare copy and latter
check proofs.
Classes of work.
Ø
Book work--Mainly
mechanically set, with uniform make-up and a limited amount of hand-set matter.
Ø
Periodicals and
magazine; Edition matter mechanically set.
Ø
Jobbing; any such
work may be hand-set entirely or contain machine cost.
Two or more colour.
When work is to be printed in
two or more colour, time must be allowed for registration. For jobs with only a
few times of types or rules in a second colour, each colour form should be
assessed separately, and a little extra added to cover the cost of fitting the
form.
Book work;
The following points must be decided;
Ø Area of type on page.
Ø Size of type for text matter, extras footnotes etc.
Ø Number of pages for preliminary matter.
Ø Extras.
There are three main stages in the preparation of the estimate;
1) Casting-off the copy to
determine the number of pages.
2) Casting-up to ascertain the
amount of mechanical setting and handwork.
3) Calculating operational
times.
Periodicals and Magazine
A systematic approach is particularly important in this field demanding thorough break
down of the work involved into the operations element. There are two main
sub-division to be considered—editorial matter and advertisements;
In estimating for a
periodical it should be remembered that
the simpler
the final schedule, the more likely it is to please the publisher.
Editorial
Matter
Ø Determine the page size.
Ø Range of type sizes for
editorial matter.
Ø Style of setting of
editorial matter, number of column etc.
Ø Extent of display.
Ø Number of color.
Ø Classified advertisement
type size, layout etc.
New setting; Assess setting time allowing for corrections, make up proofing and
imposition on a page basis.
Complete block; Time should be allowed for main ting pooling a
proof possible repair and imposing. Any caption setting should also be
included.
Repeat Advertisement; Depending on the frequency of the periodical,
a statement should appear in the schedule as to how long an advertisement will
be kept standing before it will be treated again as new setting. Times should
be assessed for pulling a proof, making good any batters and imposing.
Jobbing; Jobbing constitutes a large part of print. Until experience has been
gained computing time values by comprehensive assessment, a systematic approach
should be practiced. Work should be divided into pages or section and their
value assessed separately.
Supplementary expenses; The composition times include a normal number of
ordinary proofs (actually) up to four in black. If additional proofs are
required, the extras time tuber in pulling and the small cost of paper should
be included in the estimates.
When
proofs are such a character that they have to be pulled in the machine, time at
the hourly rate of the machine must be estimated.
PRODUCTION PLANNING
- OVER-VIEW
THE SCOPE AND POSITION OF
PRODUCTION-PLANNING
The objective of production planning
The objective of production planning is to
satisfy customer delivery dates at minimum overall cost by planning the
sequence of production activities.
This
may be broken down into a number of constituent objectives;
Ø To plan the supply of machines; Parts and components so that they are brought together at the right time
in the right work location.
Ø To make the most economical use; Plant and equipment by
smoothing out production and scheduling to the best machine utility.
Ø To combine with marketing staff; in fulfilling marketing
plan by spot lighting unbalanced production, shortage and sales activity
requirements.
Ø To arrange for the best of labouring; fulfilling the sales order book promises.
Ø To provide information services; for production management
on procedure, manufacturing instruction, routes and other background production
Ø To supply up-to-date statements; of the progress of all
orders through the factory.
Ø To plan for provision of adequate finished goods stocks according to
marketing needs
Production Control System: The sequence of
activities in manufacturing starts with long-range marketing plans, made in
accordance with the objective and strategy of the company, and ends with
historical accounting of what has been achieved. The steps in this sequence are
as follows:
Ø Long-range planning
Ø Short-range planning
Ø Preparation for
manufacture(production planning)
Ø Manufacturing
Ø Distribution
Ø Control accounting (feed-back)
The position of production planning: The position in the system
depends on the business. The system may
be sophisticated with many interacting sub-system, or very simple, as in the
small firm. Where a separate production planning department is organized then
it normally concentrates on all production information for a product
manufacturing sequence from the sales schedule to invoicing.
Production planning/ sales interface: The
sales system is an interacting system with production planning. This means that
the interface between the systems should be as fluid as possible. At
best they will work as one unit.
THE INIATION OF PRODUCTION
The initial Decision:
In the first instance, production
of a few products may be either the launching of a new line by the company
itself or the receipt of a contract from a customer, or the acceptance
of a tender which has already been prepared and submitted by the
company.
In the first case and to a large extent in
the third the conception of the new product will result from the combination
of:
Ø Technical and
Ø Marketing consideration
The marketing function will have investigated
the market needs for the product or may even have suggested the idea themselves
The technical and design staff have designed
and developed a product to suit that market.
LETTERPRESS ORIGINALS AND
DUPLICATE PLATES
ORIGINALS: Frequently new blocks have to be supplied by the
printers. Estimates of the cost must be given, and usually quotations have to
be obtained from block makers. Process engraving covers the making of blocks to
be printed by letterpress methods. The two main aspect of process engraving
cover line blocks and half - tone blocks. Take every opportunity of checking or
scrutinizing invoices received from block makers to eventually come to
appreciate the possibilities of process engraving, and to understand the method
of applying a price list with its many incidentals and EXTRAS to actual or
potential work for which one is required to prepare quotations.
When
making an estimate some thought should be given to the suitability of originals
for the process for which they are to be used without further retouching or
alternations, and whether artwork sibs to scale.
Size required: Block making allows enlargement or reduction of an original as well as
reproduction in the same size. Size is understood to mean linear scale, not
area, the reduction or traceries, is therefore is in exact proportion to the
original.
Calculating the cost of
originals; The cost of block top the printer will normally be the net amount of the
bookmaker scale charges (be a less the agreed trade discount) plus a % for
outwork expenses.
The first step is to measure the image area
each subject if it is irregular in shape, find the smallest rectangle which
will contain the subjects.
A
common source error, when quoting for new blocks, is the omission of incidental
charges. These can be complex and therefore block making should never be quoted for by anyone who does not fully
understand the pricing system. It is possible for incidental charges to be
equal or higher than the basic price.
Proofing - Extra proofs may have to be allowed for.
Color separation - An extra charge is made for panchromatic negatives in color line and
black/white line work.
BLOCKS SUPPLIED BY CUSTOMER—For half tone block the screen should be known, as this may affect the
paper to be used for the job. Frequently blocks must be pierced, stepped for
type insertion, or be mounted on metal.
Variation
in the quality of work produced from blocks supplied by customers is after
covered by a clause in the condition which accompanies the quotation.
When
a customer proposes to supply blocks for the printing of three or four color
half tone work, or multicolored line work, the estimator should stipulate that a
set of progressive proofs or, or block makers color-guides should also be
supplied, otherwise preliminary machine proofing may be necessary.
Existing blocks—when estimating for re-print, care should be taken to ensure that stored
are in good condition, as otherwise make ready may take longer, or the blocks
themselves may have to be replaced.
HINTS OF THE ESTIMATOR.
When
a job involves intricate make up, with many different type faces and blocks it
may be more economical it make time blocks of the type matter and mount on
metal.
In preparing a quotation for the
customer, a separate price may be quoted for blocks and artwork, or their cost
be included in their calculations without separating them from the charge for
printing.
FACTORS AFFECTING CHOICE OF
DUPLICATES.
*Having
decided that some form of duplication desirable either wholly or in part, the
next step is to determine the kind of duplicates wanted
*It
will be necessary to consider the nature of the job
whether it will consist of type matter, blocks or a mixture of both.
*The durability of duplicates plate (or blocks) depends on
many factors.
FACTORS AFFECTING THE COST OF DUPLICATE
PLATES.
Cost
based on size. Find the smallest rectangle which will contain the subject
except that the narrow dimension is considered to be not less than 50mm when
the long dimension exceeds 600 mm. Price list state basic prices indicating whether
mounted or un mounted plates involved.
LETTER PRESS
MACHINE WORK
Machining relates to all those operations carried out in the department which are
directly chargeable to the job. The way in which a job may be printed depends
on the working size of the sheet and the imposition
scheme, and will involve working on one side, half sheet work (work in
turn), sheet work etc.
Chargeable
operations will cover; Make ready and pre-make ready (if
this is done by the machine department) output times for running, including provision for special
wash-ups, charged at the hourly rate for the particular machine.
Selection
of machine;
Whenever
possible machines should be used to their fullest capacity. Full information
should be available on the capacities of the plant, its current production
programme, and the average outputs of the machines on the classes of work for
which they are most suited.
Details which must be known (about machine) include;
Ø The
size of bed.
Ø The
largest and smallest sheet handled.
Other considerations determining the choice of
machine are;
Ø The
nature of the fame.
Ø Suitability of inking.
Ø Hourly cost rates of different machine.
Making ready—the total makes ready time will depend
not only on the size of machine and nature of the forme,
but also the extent and standard of the pre-make ready.

The
following operations must take place for each forme
on all work other than possibly cheapest quality job;
Ø Re-dressing
cylinder or tympana.
Ø Loading forme
into position.
Ø Position forme
on to paper.
Ø Leveling
impression.
Ø Prepares machine to run load feeder and set
the gripper.
Ø Ink-up
machine and start run.
Ø Overseers check and pass for running on.
Ø Lift
job and end of run.
·
Wash-up including duct.
·
Clean machine
down.

Mounting
plates;
In
formes which consists of plates only, such as the yellow, magenta and the cyan
of four color process work, the plates can be mounted on to patent metal bases.
This work can be done as part of pre-make-ready or in the composing department.
The times for this work if part of
pre-make-ready are as follows;
|
Up to A2(minutes)
|
Up to A1(minutes)
|
Over to A1(minutes)
|
Local base
|
20
|
30
|
40
|
Lay plates
and initial register 6 minutes per plate with a minimum of
|
15
|
15
|
15
|
Output;
Output
expressed as the number of sheets netted per hour will depend on the quality of
work, stock of paper or board and also the condition of the machine. It is
useful to complete output records of the different machines within a firm.
Running speed must not be accepted as output incidental stoppages are common.
PLANNING
AND CONTROL.
The quality and efficiency of every printing operation is affected by the
structure of the organization, equipment, policies, planning and systems of
control in which it is performed. The environment in which a product is
manufactured starts with the plant facilities and work place equipment. It also
includes the organizational structure and procedures by means of which funds,
people, equipment and materials are obtained and managed for productive
purposes.
Organizational controls for the production processes are often
categorized as PRODUCTIONCONTROL and QUALITY CONTROL.
Production control consists of the mechanics forms, devices, and
specified procedures by which the flow of work is effectively through its various stages.
Job estimating is an adjunct to production control. Quality control
consists of the specifications, devices, and inspection by which quality
standards are maintained throughout the entire production process.
PLANT AND WORK
PLACE
The subjects of plant design and layout do not arise very often in a
given company.
Special attention is given here to the principles of plant layout that
are generally applicable to most lithographic plants.
Factors to be considered when choosing a plant location are;
PLANT LAYOUT
Regarding plant layout, the consideration is whether the planning s for a
new building or an existing one. The building should be thought of as part of
production machine and a new structure should be built to fit a predesigned
layout planned for the best possible production flow.
The first principle of plant layout is to provide for direct product flow
with minimum travel from one operation to the next, without backtracking.
Material handling, or the movement of product through a printing plant, is
estimated to account for 60% of all direct and indirect labor costs.
The second principle of plant layout is separation office and
manufacturing function. All pre-press operations are included in the office
category. The distinction is based on the needed for cleanliness and quite in
office areas versus the large noisy, often high-ceiliorged and heavily
trafficked environment of the manufacturing areas.
Office and pre-press areas are designed to promote concentration on
particular tasks. The type of environment suited for estimating, accounting,
and other traditional office operations has long been understood.
The plate room atmosphere is kept free of anti setoff powder. The
creative areas are kept free of noise and work-in-process traffic. The
manufacturing areas should also be kept free of unnecessary visits from
customers. The two functions might be housed in separate buildings or have a
distinct separation within a building, with a long corridor or hallway between
them.
Providing for expansion without damaging established layout principles is
an important consideration of plant layout.
If the office or prepress and the manufacturing functions have been established
in a separated but side-by-side direct flow manner, and space is available for
outward expansion of a particular capacity, such as that of a pressroom then
such expansion can be made without disrupting the overall pattern already in
effect in the printing plant.
EQUIPMENT
AND WORKPLACE
Policies and procedures for the acquisition, arrangement, and maintenance
of equipment play a vital role in effective operations. Equipment addition and
replacement policies are part of financial planning. At this point attention is
given only to the matters considered in choosing a particular piece of
equipment after the decision to add or replace has been made. The first
equipment is that the equipment will perform the needed functions adequately.
Adequate should include safety, speed, and quality considerations.
The price of the equipment and the cost of its installation must be
evaluated when assessing whether its cost lies within available capital
resources. A skill innovatory survey of the work force for estimating the
financial allocation necessary not only for outside installers, but also for
hiring or training, maintenance and operating personnel for the new equipment
is recommended.
Maintenance
Management is another aspect of equipment that needs to be planned.
In a large plant, there is usually a maintenance department. But even if a
plant is not big enough to have a separate maintenance department, it should
have an organized maintenance function. In the face of increasing mechanization
and complexity, higher production control and delivery schedules and stricter
quality requirements, good maintenance control becomes increasingly important.
On the theory that it is cheaper to prevent breakdowns than to repair them, the
organization of maintenance should be built around Preventive Maintenance.
Preventive
Maintenance, which is more commonly associated with the
maintenance of machinery, consists of scheduled inspection, cleaning
lubrication, and parts adjustment, repair, or replacement. Generally machinery needs
frequent inspection while it is new and when it is very old. Other factors that
should affect the inspection schedule include the heaviness of use and the
value of equipment. A carefully established lubrication schedule for each
machine is important. The manufacturer’s instructions should be followed
regarding type of lubricant and frequency of lubrication. Use of a lubrication
chart for routine lubrication is essential. Special lubrication needs are
sometimes discovered during inspections, which also help to uncover part repair
or replacement needs.
PEOPLE AND
ORGANIZATION.
If one element could be considered most important among the several
essential elements in an organization, that element probably would be people
and their management.
They include employee recruitment, any training of job incumbents,
provision of facilities, compensation, and supervision, evaluation of job
performance, motivation and advancement.
Recruitment consists of searching for and attracting qualified applicants
and then selecting those most suitable. Prospective employers can provide
guidance in curriculum development and make their own organizations more
attractive than to prospects by providing informational and cooperative
activities with prospect-source organization.
Selection has two aspects;


These later procedures include testing, evaluating past performance, and
developing effective interviewing techniques.
Even persons who are already trained and experienced in the type of work
they will be doing; will need some in-house training concerning the company and
its particular equipment and procedures.
Others will need more extensive training. Organization that are not large
enough to employ a training director should make sure that new employee
instruction is not left to haphazard practices. Management should provide
guidelines for training procedures.
Policies that recognize employee
worth and encourage participation through suggestion systems work
simplification programs, or quality circles can enhance motivation and employee
effectiveness.
No comments:
Post a Comment